In the Operation & Maintenance (O&M) business, Medco Power Indonesia has been successful in improving the plant availability factor rate at the Tanjung Jati B coalfired power plant in 2012 to 95%, higher than the plant availability factor rate of 92% achieved in 2011. MPI was also able to maintain Zero Accidentin the operation of Tanjung Jati B power plant with total work-hours of 11,601,976 hours up until year-end 2012, as well as obtaining Blue PROPER certification from the Ministry of Environment of the Republic of Indonesia. Meanwhile, in the EPC business.